Guide for clients

Client duties for construction work in South Africa

Last updated:

On this page
  1. What does regulation 1 of the Construction Regulations say a client is?
  2. What counts as construction work?
  3. What does a client have to do before construction work starts?
  4. What is a health and safety specification?
  5. What is a baseline risk assessment, and who prepares it?
  6. Does a client have to check the contractor during the work?
  7. What do the Construction Regulations say about a client's agent?
  8. When does construction work need a permit or a notification?
  9. Is repainting, a new roof or a shop fit out construction work?
  10. Where does Manage Safety fit for a client?
  11. What Manage Safety does and does not do
  12. How do I start with my client duties?

If you are paying for building, alteration or maintenance work in South Africa, the Construction Regulations, 2014 may name you as a client, with a list of duties of your own. This guide sets out, in the regulations' own words, who a client is, what the list holds and what the regulations say about permits and notifications. Manage Safety is a record keeping tool, so we also say where it helps and where it does not.

What does regulation 1 of the Construction Regulations say a client is?

Regulation 1 of the Construction Regulations, 2014 reads:

“client” means any person for whom construction work is being performed;

The words do not mention size, trade or whether you own the property. The quoted words turn on whether construction work is being performed for you. The word used is “any person”, and whether a company, a body corporate or a trust counts is something a consultant or attorney can confirm. Whether you are in that position on your own facts is a question for a health and safety consultant or an attorney. For the same question from the property owner's side, see construction clients.

What counts as construction work?

The same regulation of the Construction Regulations, 2014 defines it:

“construction work” means any work in connection with - (a) the construction, erection, alteration, renovation, repair, demolition or dismantling of or addition to a building or any similar structure; or (b) the construction, erection, maintenance, demolition or dismantling of any bridge, dam, canal, road, railway, runway, sewer or water reticulation system; or the moving of earth, clearing of land, the making of excavation, piling, or any similar civil engineering structure or type of work;

Two things stand out. The first part covers more than a new build: alteration, renovation and repair of a building are named. The second part reaches past buildings, to roads, sewers, excavation and the clearing of land.

What does a client have to do before construction work starts?

Regulation 5(1) of the Construction Regulations, 2014 begins “A client must-” and then lists items. Several of them are worded around the start of the work. The client must prepare a baseline risk assessment for an intended construction work project, and a site specific health and safety specification for the intended work, based on that assessment. The client must see that the principal contractor to be appointed has the necessary competencies and resources to carry out the construction work safely. The client must also make sure, before any work commences on a site, that every principal contractor is registered and in good standing with the compensation fund or with a licensed compensation insurer, and must appoint every principal contractor in writing for the project or part of it.

That is a selection. The quoted words skip some paragraphs, which you can see marked in the Sources list at the end of this page, so read the regulation itself or ask your consultant for the full list. For the contractor's side of the same project, see Manage Safety for principal contractors.

What is a health and safety specification?

The words of regulation 5(1) of the Construction Regulations, 2014 describe it only in outline:

(b) prepare a suitable, sufficiently documented and coherent site specific health and safety specification for the intended construction work based on the baseline risk assessment contemplated in paragraph (a);

So the specification is for the intended construction work, it is specific to the site, it is based on the baseline risk assessment, and it has to be suitable, sufficiently documented and coherent. The wording quoted on this page does not say what a specification must contain. That depends on the work, and a health and safety consultant who has seen the project can tell you.

What is a baseline risk assessment, and who prepares it?

The same list answers the second half. Regulation 5(1) of the Construction Regulations, 2014 says:

(a) prepare a baseline risk assessment for an intended construction work project;

The duty is the client's. The wording quoted here does not define a baseline risk assessment or say how detailed it must be. Both depend on the project, so that is for your consultant. The next item says the specification is “based on the baseline risk assessment”.

Does a client have to check the contractor during the work?

Two items in regulation 5(1) of the Construction Regulations, 2014 speak of the period after work is under way:

(n) take reasonable steps to ensure that each contractor's health and safety plan [...] is implemented and maintained; (o) ensure that periodic health and safety audits and document verification are conducted at intervals mutually agreed upon between the principal contractor and any contractor, but at least once every 30 days;

The first is about reasonable steps. The second names a minimum frequency, at least once every 30 days, within intervals agreed between the principal contractor and any contractor. Who carries out an audit is not stated in these words, and Manage Safety does not perform audits. A consultancy does.

What do the Construction Regulations say about a client's agent?

The regulations speak of an agent. Where a construction work permit is required, regulation 5(5) of the Construction Regulations, 2014 reads:

(5) Where a construction work permit is required [...], the client must, without derogating from his or her health and safety responsibilities or liabilities, appoint a competent person in writing as an agent to act as his or her representative [...]

And regulation 5(6) of the Construction Regulations, 2014 deals with notification of construction work:

(6) Where notification of construction work is required [...], the client may, without derogating from his or her health and safety responsibilities or liabilities, appoint a competent person in writing as an agent to act as his or her representative [...]: Provided that, where the question arises as to whether an agent is necessary, the decision of an inspector is decisive.

Read the words “without derogating from his or her health and safety responsibilities or liabilities”. In both provisions the appointment is made without giving up the client's own responsibilities or liabilities. The quoted words also say that, where an agent is appointed, the client's duties apply as far as reasonably practicable to the agent. Where a permit is required the wording is “must”. Where notification is required it is “may”, and an inspector's decision is decisive on whether an agent is necessary. What this means for a particular project is something a consultant or attorney can confirm.

When does construction work need a permit or a notification?

The Construction Regulations, 2014 speak of both, and they are two different provisions. Regulation 3(1) of the Construction Regulations, 2014 is about a permit:

  1. (1) A client who intends to have construction work carried out, must at least 30 days before that work is to be carried out apply to the provincial director in writing for a construction work permit to perform construction work if the intended construction work will- (a) exceed 180 days; (b) will involve more than 1800 person days of construction work; or (c) the works contract is of a value equal to or exceeding thirteen million rand or Construction Industry Development Board (CIDB) grading level 6.

Notice who the words are addressed to: a client. The three conditions are listed with “or” between them. Regulation 4(1) of the Construction Regulations, 2014 is about notification:

  1. (1) A contractor who intends to carry out any construction work other than work contemplated in [...], must at least 7 days before that work is to be carried out notify the provincial director in writing in a form similar to Annexure 2 if the intended construction work will- (a) include excavation work; (b) include working at a height where there is risk of falling; (c) include the demolition of a structure; or (d) include the use of explosives to perform construction work.

Here the words are addressed to a contractor, and the work in question is “any construction work other than work contemplated in regulation 3(1)” of the Construction Regulations. This guide does not work out for you whether your project meets any of these conditions. The number of days, the number of person days and the value of the contract come from your project, so ask your consultant to measure them.

Is repainting, a new roof or a shop fit out construction work?

The definition above names alteration, renovation and repair of a building, so these jobs are not outside the words just because they are not a new build. Whether a particular repaint, a new roof or a shop fit out is “work in connection with” one of those things depends on exactly what is being done, where, and how much of it. Whether it then needs a permit or a notification depends on its length, its size and its contract value, and on whether it includes things such as excavation or work at a height.

Nobody can answer that without the details of your job. A health and safety consultant works it out from them, or an attorney if it turns on a contract. Once the answer is known, Manage Safety can hold the site, the contractor records and the dates that follow from it. If you have no consultant, we can introduce you to one. Book a free walkthrough and bring your quote and whatever drawings you have.

Where does Manage Safety fit for a client?

A site in Manage Safety is its own record, with its own documents and its own appointments. The Sites list shows a count of expired and expiring documents for each site, and a site can be shared with another company for reading, so a client and a contractor can look at the same site's documents. A document with an expiry date is marked by colour, expired or expiring soon, which means today or within the next 60 days, and it never disappears because it expired.

One honest limit. Manage Safety holds what you put in it. It does not decide whether you are a client, whether a permit is needed or what your specification must say. If you hire contractors for other kinds of work as well, read hiring contractors.

What Manage Safety does and does not do

We do not give legal advice. We do not make anyone compliant, and we do not write your specification or your baseline risk assessment. We do not perform audits. A consultancy does that. A health and safety consultant works out which duties apply to your project.

What we do is keep the records and the dates in one place, set up with you, so you can see what has been filed and what has lapsed. Expiry shows by colour on the record, so somebody needs to look. Do not rely on an email before each document expires. If you need a consultant, you can start at find a consultant.

How do I start with my client duties?

Book a free walkthrough. We look at your situation with you, and we tell you honestly whether Manage Safety fits before you pay anything. We set your account up and invite you ourselves, because there is no public sign up.

Book a free walkthrough

What the regulation says

1. [...] “client” means any person for whom construction work is being performed; [...] “construction work” means any work in connection with - (a) the construction, erection, alteration, renovation, repair, demolition or dismantling of or addition to a building or any similar structure; or (b) the construction, erection, maintenance, demolition or dismantling of any bridge, dam, canal, road, railway, runway, sewer or water reticulation system; or the moving of earth, clearing of land, the making of excavation, piling, or any similar civil engineering structure or type of work;

Construction Regulations, 2014 (Government Notice R84, Government Gazette 37305 of 7 February 2014), regulation 1, definitions, 1

5. (1) A client must- (a) prepare a baseline risk assessment for an intended construction work project; (b) prepare a suitable, sufficiently documented and coherent site specific health and safety specification for the intended construction work based on the baseline risk assessment contemplated in paragraph (a); [...] (h) ensure that the principal contractor to be appointed has the necessary competencies and resources to carry out the construction work safely; [...] (j) ensure before any work commences on a site that every principal contractor is registered and in good standing with the compensation fund or with a licensed compensation insurer as contemplated in the Compensation for Occupational Injuries and Diseases Act, 1993 (Act No. 130 of 1993); (k) appoint every principal contractor in writing for the project or part thereof on the construction site; [...] (n) take reasonable steps to ensure that each contractor's health and safety plan [...] is implemented and maintained; (o) ensure that periodic health and safety audits and document verification are conducted at intervals mutually agreed upon between the principal contractor and any contractor, but at least once every 30 days;

Construction Regulations, 2014 (Government Notice R84, Government Gazette 37305 of 7 February 2014), regulation 5(1), 5(1)

5. [...] (5) Where a construction work permit is required as contemplated in regulation 3(1), the client must, without derogating from his or her health and safety responsibilities or liabilities, appoint a competent person in writing as an agent to act as his or her representative, and where such an appointment is made the duties that are imposed by these Regulations upon a client, apply as far as reasonably practicable to the agent so appointed.

Construction Regulations, 2014 (Government Notice R84, Government Gazette 37305 of 7 February 2014), regulation 5(5), 5(5)

5. [...] (6) Where notification of construction work is required as contemplated in regulation 4(1), the client may, without derogating from his or her health and safety responsibilities or liabilities, appoint a competent person in writing as an agent to act as his or her representative, and where such an appointment is made the duties that are imposed by these Regulations upon a client, apply as far as reasonably practicable to the agent so appointed: Provided that, where the question arises as to whether an agent is necessary, the decision of an inspector is decisive.

Construction Regulations, 2014 (Government Notice R84, Government Gazette 37305 of 7 February 2014), regulation 5(6), 5(6)

3. (1) A client who intends to have construction work carried out, must at least 30 days before that work is to be carried out apply to the provincial director in writing for a construction work permit to perform construction work if the intended construction work will- (a) exceed 180 days; (b) will involve more than 1800 person days of construction work; or (c) the works contract is of a value equal to or exceeding thirteen million rand or Construction Industry Development Board (CIDB) grading level 6.

Construction Regulations, 2014 (Government Notice R84, Government Gazette 37305 of 7 February 2014), regulation 3(1), 3(1)

4. (1) A contractor who intends to carry out any construction work other than work contemplated in regulation 3(1), must at least 7 days before that work is to be carried out notify the provincial director in writing in a form similar to Annexure 2 if the intended construction work will- (a) include excavation work; (b) include working at a height where there is risk of falling; (c) include the demolition of a structure; or (d) include the use of explosives to perform construction work.

Construction Regulations, 2014 (Government Notice R84, Government Gazette 37305 of 7 February 2014), regulation 4(1), 4(1)